Jiangbei New District Comprehensive Pipe Gallery Phase II Project, Nanjing City, Jiangsu Province
The second phase of the comprehensive pipe gallery in Jiangbei New District, Nanjing City, Jiangsu Province, has completed the installation of terminal equipment in the gallery and entered the machine room scheduling system for debugging.
The total length of the comprehensive pipe gallery planned and constructed in Jiangbei New Area is 241 kilometers, including 63 kilometers in the core area. The first phase has been completed for 10 kilometers. The second phase is planned to construct 53 kilometers, including main and branch pipe galleries, with a total investment of 5.8 billion yuan. The main comprehensive pipe gallery is 31 kilometers and the branch comprehensive pipe gallery is 22 kilometers. The project started in September 2016 and is expected to be completed in 2021. It is being constructed by the Jiangbei New Area Public Works Construction Center.